How to do ANP: building the supermatrix and reading the limit priorities
The Analytic Network Process step by step: interdependent criteria, local priorities, the unweighted and weighted supermatrix, and the limit priorities.
CKR team · · 9 min read
The Analytic Network Process (ANP) extends AHP to criteria that influence each other. For each element, the elements that influence it are compared in pairs, and the resulting local priorities form one column of the supermatrix. The columns are made to sum to 1 (the weighted supermatrix W), and W is raised to powers until it stabilises: every column of the limit supermatrix then holds the same vector, which satisfies w = Ww and gives the overall priorities.
The short version
- 01Each column of the supermatrix holds the priorities of the elements that influence the column element, from a small AHP comparison.
- 02The weighted supermatrix has columns summing to 1; when the network has clusters, cluster weights scale the blocks first.
- 03The limit priorities are the vector w with w = Ww, reached by raising W to powers; in the supplier example Quality 0.346, Cost 0.302, Delivery 0.212, Service 0.140.
- 04Compared with AHP’s independent weights (Quality 0.497), dependence moves weight towards criteria that others depend on, such as Delivery and Service.
- 05ANP needs many more judgements than AHP; use it when the dependence is real and can be stated by the experts.
When do you need ANP instead of AHP?
AHP arranges a decision as a hierarchy: a goal, criteria beneath it and alternatives at the bottom, with each level judged with respect to the one above. It assumes that the criteria are independent: how important Quality is does not depend on how the supplier performs on Cost. Often that assumption is false. A supplier’s delivery reliability affects the service it can offer; the quality of its products affects its costs through rework. When criteria influence each other, a hierarchy cannot represent the problem.
The Analytic Network Process (ANP), developed by Saaty (1996), replaces the hierarchy with a network. Elements can influence elements in other groups and in their own group, and influence can run in loops. All the judgements are still pairwise comparisons on Saaty’s scale, but they are collected into a single matrix, the supermatrix, whose long-run behaviour gives the priorities. Saaty and Takizawa (1986) showed how dependence among criteria changes the weights a hierarchy would give, and that idea is the starting point of this tutorial.
- 01Map the influencesFor each element, which elements influence it (or matter with respect to it)?
- 02Local prioritiesFor each element, compare the elements that influence it in pairs; check consistency.
- 03Unweighted supermatrixPut each element’s local priorities in its column.
- 04Weighted supermatrixScale blocks by cluster weights if there are clusters; make each column sum to 1.
- 05Limit supermatrixRaise W to powers until the columns stop changing; read the priorities from any column.
What example will we use?
The example takes the four supplier criteria used in the VIKOR and PROMETHEE tutorials: Cost, Quality, Delivery and Service. In the hierarchical AHP analysis behind those tutorials, the purchasing manager’s weights were Quality 0.497, Cost 0.314, Delivery 0.121 and Service 0.069, with the criteria treated as independent. Asked instead how the criteria depend on each other, the manager identified influence in every direction: quality and delivery problems drive cost; cost pressure affects quality and service; delivery reliability shapes service. The network is a single cluster of four elements with inner dependence.
Step 1: how do you get the local priorities?
For each criterion, ask: with respect to this criterion, which of the other criteria matters more, and by how much? For Cost the question is “in its influence on our costs, how much more important is Quality than Delivery?”, and similarly for the other pairs. With four criteria, each criterion has three others to compare, so each column needs a 3 × 3 AHP matrix. The four matrices below happen to be perfectly consistent (CR = 0), which keeps the numbers simple; real judgements will not be.
| With respect to | Elements compared | Judgements | Local priorities | CR |
|---|---|---|---|---|
| Cost | Quality, Delivery, Service | Q = 2·D, Q = 6·S, D = 3·S | 0.600, 0.300, 0.100 | 0.000 |
| Quality | Cost, Delivery, Service | C = 2·D, C = 2·S, D = S | 0.500, 0.250, 0.250 | 0.000 |
| Delivery | Cost, Quality, Service | C = Q, C = 4·S, Q = 4·S | 0.444, 0.444, 0.111 | 0.000 |
| Service | Cost, Quality, Delivery | Q = 2·C, C = D, Q = 2·D | 0.250, 0.500, 0.250 | 0.000 |
Note. Each row is one 3 × 3 AHP matrix; “Q = 2·D” means Quality is judged twice as important as Delivery with respect to the column criterion.
Read the first row as the manager’s view of what drives cost: quality matters most (0.6), delivery next (0.3), service little (0.1). Each set of local priorities sums to 1. In a larger network, the consistency ratio of each of these small matrices should be checked exactly as in AHP; the consistency-ratio tutorial shows how.
Step 2: how do you build the supermatrix?
Write the elements along both the rows and the columns, in the same order. The column for an element holds the local priorities of the elements that influence it, and zeros elsewhere. Here no criterion is compared with itself, so the diagonal is zero.
| Cost | Quality | Delivery | Service | |
|---|---|---|---|---|
| Cost | 0.000 | 0.500 | 0.444 | 0.250 |
| Quality | 0.600 | 0.000 | 0.444 | 0.500 |
| Delivery | 0.300 | 0.250 | 0.000 | 0.250 |
| Service | 0.100 | 0.250 | 0.111 | 0.000 |
The orientation matters and is a frequent source of confusion. In the ANP convention used by Saaty and in CKR, columns are the “with respect to” elements and each column sums to 1. A matrix entered the other way round, with rows summing to 1, describes a different network and gives different priorities.
Step 3: when do you need a weighted supermatrix?
In this example every column already sums to 1, because the network has one cluster and each column holds one set of local priorities. In larger networks the elements are grouped into clusters, for example criteria and alternatives, and a column may contain local priorities from several clusters, each block summing to 1. The column then sums to more than 1. The clusters are compared in pairs as well, and the resulting cluster weights scale each block so that every column of the weighted supermatrix W sums to 1. CKR expects that cluster weighting to be applied before the matrix is entered, and rescales every column to sum to 1.
Step 4: how do you compute the limit supermatrix?
Multiplying W by itself traces influence along paths of length two: W² holds the influence of each element on each other element through one intermediary, W³ through two, and so on. As the power grows, the columns of Wᵏ converge to the same vector, which is the long-run share of influence each element receives through the whole network.
| Power k | Cost | Quality | Delivery | Service |
|---|---|---|---|---|
| 1 | 0.0000 | 0.6000 | 0.3000 | 0.1000 |
| 2 | 0.4583 | 0.1833 | 0.1750 | 0.1833 |
| 3 | 0.2153 | 0.4444 | 0.2292 | 0.1111 |
| 4 | 0.3519 | 0.2866 | 0.2035 | 0.1581 |
| 8 | 0.3079 | 0.3385 | 0.2112 | 0.1424 |
| 12 | 0.3028 | 0.3448 | 0.2120 | 0.1404 |
| limit | 0.3021 | 0.3456 | 0.2121 | 0.1402 |
The values swing at first, because influence passes back and forth around the loops, and settle by about the twelfth power. Every other column converges to the same limit. CKR computes the limit directly as the stationary vector, using a damped iteration that also converges when W is cyclic, and checks that the result satisfies w = Ww; for this matrix the remaining error is below 10⁻¹⁴.
Show the data
| Criterion | Limit priority |
|---|---|
| Quality | 0.3456 |
| Cost | 0.3021 |
| Delivery | 0.2121 |
| Service | 0.1402 |
How do the ANP priorities compare with AHP?
| Criterion | AHP (independent) | One step: W·w_AHP | ANP limit |
|---|---|---|---|
| Cost | 0.3135 | 0.3194 | 0.3021 |
| Quality | 0.4967 | 0.2763 | 0.3456 |
| Delivery | 0.1213 | 0.2354 | 0.2121 |
| Service | 0.0685 | 0.1690 | 0.1402 |
Note. The one-step column applies the dependence once to the AHP weights (Saaty & Takizawa, 1986), normalised to sum to 1.
Allowing for dependence moves weight away from Quality and towards Delivery and Service. The reason is visible in the supermatrix: Delivery and Service matter with respect to every other criterion, so in a network they gather influence that the hierarchy did not credit them with. Quality remains the largest single priority but falls from about half the total to about a third. The one-step weights, which apply the dependence matrix once to the AHP weights, sit in between and still depend on the manager’s direct judgements; the limit priorities depend only on the network judgements.
How sensitive are the limit priorities to one column?
Because every column feeds the limit, a change in one set of local priorities moves all the final weights. Suppose the manager had judged that quality and delivery drive cost equally (Q = D, each four times as important as service), so the Cost column becomes 0.444, 0.444, 0.111 instead of 0.6, 0.3, 0.1. Recomputing gives Quality 0.313, Cost 0.301, Delivery 0.247 and Service 0.139. Quality’s priority falls by 0.033 and Delivery’s rises by 0.035, while Cost and Service barely move; Quality still ranks first, but its lead over Cost shrinks to 0.012.
This is a useful pattern to test in any ANP study: change each column within a range the experts would accept, recompute the limit, and report which priorities are stable. A conclusion such as “quality is the most important criterion” should only be drawn if it survives such changes. In this example it does, though only narrowly.
Which mistakes are common in ANP studies?
- Entering the supermatrix transposed, with rows instead of columns summing to 1.
- Leaving a column of zeros, for an element that nothing is judged with respect to. The limit is then not defined; every element needs at least one set of local priorities.
- Forgetting cluster weights in a multi-cluster network, so that clusters with more elements dominate.
- Not checking the consistency of the many small comparison matrices. Each one is an AHP matrix and needs a CR.
- Claiming dependence without asking the experts about it. ANP is only as good as the influence map behind it.
How many judgements does ANP need?
Considerably more than AHP. With four criteria, AHP needs 6 comparisons; this ANP network needed four 3 × 3 matrices, 12 comparisons. A realistic model with three clusters of five elements can require several hundred, and experts tire quickly. Keep the network to the dependences that the experts can state with confidence, and consider DEMATEL to identify which influences are strong enough to include before building the supermatrix, a combination often called DEMATEL-based ANP.
How do you report ANP?
Report the network structure, preferably as a diagram, the question asked for each comparison, every comparison matrix with its consistency ratio, the unweighted and weighted supermatrix, the cluster weights if any, and the limit priorities. Cite Saaty (1996) for the method. For the example: “Allowing for interdependence among the criteria reduced the priority of Quality from 0.497 (AHP) to 0.346 (ANP limit) and raised Delivery from 0.121 to 0.212.” In CKR the supermatrix can be pasted directly, and the weighted supermatrix, the limit priorities and the convergence check are reported in tables.
Questions people ask
What is the difference between AHP and ANP?
AHP assumes a hierarchy of independent criteria; ANP allows dependence and feedback between elements, collects all judgements in a supermatrix and takes its limit.
Why do all columns of the limit supermatrix become the same?
Because for a connected network the powers of W converge to a matrix whose columns are all the stationary vector w = Ww: the long-run influence on each element, regardless of where it starts.
What if the supermatrix does not converge?
If the powers of W cycle, take the average of a full cycle of powers, the Cesàro limit; its columns are the same stationary vector. CKR handles this case automatically.
Do I need ANP software?
You need a tool that computes the limit correctly and keeps track of many comparison matrices. CKR takes the supermatrix and reports the limit priorities with a convergence check.
Can ANP rank alternatives?
Yes, by including the alternatives as a cluster in the network. Their limit priorities, normalised within the cluster, give the ranking.
References
Saaty, T. L. (1996). Decision making with dependence and feedback: The analytic network process. RWS Publications.
Saaty, T. L., & Takizawa, M. (1986). Dependence and independence: From linear hierarchies to nonlinear networks. European Journal of Operational Research, 26(2), 229–237. https://doi.org/10.1016/0377-2217(86)90184-0
Saaty, T. L. (1977). A scaling method for priorities in hierarchical structures. Journal of Mathematical Psychology, 15(3), 234–281. https://doi.org/10.1016/0022-2496(77)90033-5
CKR team · Chakaralaya Analytics
How this was checked. Local priorities and their consistency ratios were computed with CKR’s AHP; the limit priorities with CKR’s ANP and independently as the principal eigenvector of W, which agreed to four decimals. The powers of W and the one-step weights were computed from the same matrix. References were checked against Crossref; Saaty (1996) is a book without a DOI.